How to Audit and Improve PUE

By Anurag Singh

Updated on Nov 20, 2025

How to Audit and Improve PUE

Power Usage Effectiveness (PUE) has become one of the most important performance indicators for modern data centres. It reflects how efficiently the facility converts electrical power into usable computing output. With rising energy costs and increasing pressure to meet sustainability goals, improving PUE is no longer optional for serious data centre or colocation providers.

This guide explains how we can audit PUE properly and take practical steps to improve it using current, real-world techniques followed across the industry.

What PUE Actually Measures

PUE is calculated as:

PUE = Total Facility Energy / IT Equipment Energy

A perfect score is 1.0, meaning all power goes directly to IT hardware. Realistically, anything between 1.2 – 1.6 is considered strong for modern data centres, depending on climate and cooling design.

Step 1: Start With a Proper PUE Audit

A correct audit is more important than the final number. If the measurement is wrong, every optimisation after that becomes guesswork. A reliable PUE audit includes:

Measure Total Facility Energy

Use your building’s main utility meter or UPS input readings. If multiple power sources exist, consolidate them monthly.

Measure IT Load Separately

This includes only servers, storage, and networking equipment. Get readings from PDUs, intelligent rack power strips, or UPS output meters.

Capture Data Continuously

AI-based monitoring tools or DCIM platforms help detect fluctuations, seasonal changes, and inefficient racks long before they cause losses.

Categorise Loads

Separate cooling, UPS losses, lighting, and auxiliary systems. This helps identify which category is dragging the PUE down.

Step 2: Improve Cooling Efficiency

Cooling is usually the biggest contributor to a high PUE. Modern optimisation techniques include:

Adopt Hot/Cold Aisle Containment

This prevents air mixing and reduces the load on CRAC or CRAH units. Even partial containment gives instant efficiency gains.

Upgrade to Variable Speed Fans

Legacy chillers and CRAC units often run at fixed speeds. Variable-speed systems adjust airflow based on real-time heat output.

Use Free Cooling Where Possible

In regions with cooler climates, outside air or water-side economisers can reduce compressor usage significantly.

Seal Air Leaks

Unused rack spaces, cable gaps, and floor openings waste cold air. Blanking panels and brush grommets are cheap but effective.

Step 3: Optimise Power Distribution

A cleaner power chain reduces conversion losses.

Reduce Double Conversion Steps

Avoid unnecessary voltage transformations or layers of power conditioning equipment.

Upgrade Old UPS Units

Modern UPS systems have higher efficiency modes (up to 97–99%). Legacy units often waste 10% or more.

Improve Rack Power Distribution

Intelligent PDUs let us track overloaded circuits and rebalance equipment to prevent hotspots and energy waste.

Step 4: Improve IT Hardware Efficiency

Infrastructure efficiency is nothing if the IT load itself is outdated.

Consolidate and Virtualise

Underutilised servers consume power even when idle. Virtualisation and containerisation help achieve higher density with fewer machines.

Refresh Old Hardware

Modern CPUs and GPUs deliver more performance per watt. Even a partial refresh can reduce energy use dramatically.

Decommission Orphaned Workloads

Zombie VMs, forgotten services, and abandoned project servers quietly burn power. Quarterly cleanup prevents this.

Step 5: Use Modern Monitoring and AI Analytics

Real-time analytics helps us see patterns humans often miss.

Predictive Cooling

AI systems adjust cooling output automatically based on temperature predictions, heat maps, and future load patterns.

Capacity Planning

Advanced DCIM tools show how power and cooling behave at different rack densities. This prevents oversizing and wasted energy.

Automated Alerts

Sudden PUE spikes often indicate hardware faults, blocked airflow, or failing CRAC units.

Step 6: Build an Energy-Efficient Culture

Tools alone cannot improve PUE. A culture shift helps significantly.

Set Targets and Review Quarterly

Continuous improvement works far better than one big overhaul.

Educate Customers in Colocation Environments

Simple changes in rack layout or cable management can reduce power waste at no cost.

Maintain Equipment Regularly

Dirty filters, clogged airflow paths, and ageing components silently raise PUE over time.

Final Thoughts

Improving PUE is a long-term process, not a one-time project. A structured audit, efficient cooling strategy, modern power distribution, and smart monitoring systems create sustainable gains that benefit both operational costs and overall reliability. By adopting these practices, data centres and colocation providers can stay competitive and meet rising energy-efficiency expectations without compromising performance.